Scroll Top

Subdivision Drainage

Subdivision Drainage Engineer Auckland
DESCRIPTION

Apcon Paterson designed a stormwater road crossing thrusted under main arterial Balmoral Rd for the two new houses in background.

An engineering plan approval (EPA) for public stormwater and sewer extensions with detention/ reuse tanks, sewer pump and private drainage for building consents and site review.

Using a package pump for ground floor only we maintained gravity sewage to upper floors so most of plumbing remains functional in a power cut of any duration, increasing reliability while saving cost, power, pump size and longevity.

We dealt with a host of council related engineers for the road crossing and conflicting council bodies requirements. Prior soakage was not up to current soil soakage capacity.

Fire reports for the three storey houses including path lengths and alarm.